Visitors
193523
Thumbnail 1
Thumbnail 2
Thumbnail 3
DFDDB25A-25FF-4C3E-AAFF-20EA0122C89D_20210107000000_photos-1610074505.3415751-2-91657a
D6F46E43-5B6E-47F9-98A2-0BA582F38E52_20210106000000_photos-1609958175.482531-1-da670f
349C9E78-7EF2-4BD6-B6C9-C90FBA6C7525_20201222000000_photos-1608655167.903531-1-5c4a13
3B4F6CB0-E319-455E-AC1C-0B0DCC364115_20210621000000_photos-1624282811.4784899-1-7e78f1
Thumbnail 5
5FC226FE-48E9-4139-89DE-62989CEEA087_20210623000000_photos-1624470596.9938521-1-a19a6d
9990247B-4868-4C4A-A47B-DE5A89391AC7_20210723000000_photos-1627295309.50439-1-177a70
FE28AF47-76E3-4C43-BBFD-247ACA265EFF_20210507000000_photos-1620384951.2384071-1-02efbb
DJI_0083
DJI_0078
DJI_0077
DCIM100MEDIADJI_0017.JPG
previous arrow
next arrow
Project Details:

Diamond Materials is currently working on a one million square foot warehouse on 22 acres in Logan Township for Burlington Coat Factory. Below is the work being performed –

Topsoil stripped: 66,000 CY
Cuts to fills: 147,374 CY
Storm sewer: 11,000 LF
Sanitary sewer: 1080 LF
Waterline: 10,000 LF
Sidewalk: 15,810 SF
Belgium Block Curb: 21,635 LF
Paving: 43,000 TONS
8” Thick Loading dock and Dolly Pads =250,000 SF
Excavate and install three Basins

Project Details:

Project:

Logan South Industrial Park Lot A

 

Location: 

Logan Township, NJ 

 

Duration: 

2021 – 2022

 

Client:

Iron Hill Construction Management