Topsoil stripped: 2500 CY
Cuts to fills: 2060 CY
Storm sewer: 2605 LF
Sanitary sewer: 434 LF
Waterline: 342 LF
Paving: 2245 tons
6” Thick Concrete Pads 600 SF
Excavate and install 3940SF Bio-retention pond
Installation of a 1175 LF Chain Link Fence, Installation of 297 LF Ornamental Fence, 3 Drainage Inlets, 1 wet tap. Installed 3 Custom Flag Poles
Project:
Newark Recycling Center
Location:
Newark, DE
Duration:
April 2020 – July 2020
Client:
Delaware Solid Waste Authority
Diamond Materials is a full service and well equipped site contractor capable of successfully completing small or large projects. From a backhoe to a thirty-five cubic yard scraper, we can meet the customers needs and create what the project management teams want. Achieving results, strict attention to detail, and compliance with all laws and regulations help assure an environmentally sound and quality finished product.