N.E Front Street Bridge SR1 Milford
On the morning of Monday, January 28th Mumford and Miller Concrete, along with Diamond Materials LLC, completed the third and final deck pour on the N.E. Front Street Bridge over SR1 in Milford, Delaware. In an effort to expedite the overall completion date of the Contract, the project team decided to use a glycol heating system to keep the concrete at a consistent temperature, which allows us to pour the deck during the winter months, rather than waiting until spring. Currently, Diamond Materials is approximately 3½ months ahead of schedule and we expect to continue improving upon the overall schedule. Contact Diamond to find out how we can help you keep your next project ahead of schedule!